N Main Street at Illinois Street (HWY 240) Intersection Study

Overlay
Project Type: Capital Project Project Status: Approved and Inactive Location: N Main Street Newberg, OR 97132 See map: Google Maps

Project Manager: Will Worthey, City Manager, City of Newberg 

email: Will.Worthey@newbergoregon.gov

CURRENT STATUS:
The intersection of N Main and Illinois will see a temporary closure with traffic bollards beginning on September 15, 2025. The intersection will be closed to motor vehicle traffic only - pedestrian and bicycle traffic will still be allowed through. A more permanent closure will be considered for the future. 

This project is named I-14 in the Transportation System Plan (TSP).

n_main_and_illinois_ study area
Public Outreach
This occurred on Wednesday October 25, 2023 at the Chehalem Cultural Center Ballroom, 415 E Sheridan Street. It quickly became clear that a full study could cost ratepayers north of $100,000 and provide results that were impossible to execute in our current operating environment.
nmain_and_illinois_satellite_intersection

STATUS UPDATES

Due to ongoing changes in staffing and budget concerns, the council and administration team has provided direction to cancel the N Main at Illinois (HWY 240) Intersection Study project. A pivot to a less expensive trial closure of the intersection was suggested as an alternative approach.

October 5/2023 - Postcard notification for the N Main Street at Illinois (HWY 240) Intersection open house were mailed on 10/25/2023 to property owners and residents in the general area of this project.

August 31, 2023 - Initial outreach and project survey notification letter mailed to property owners and residents in the general area of this project.

In 2024 a drop in session occurred at the public library to test public opinion on the showcasing the concept of a trial closure - it was found to be positive. The intersection is scheduled to be closed on September 8 2025.